Bathroom partition installation plan
1. Construction preparation:
1. Materials: According to the materials processed by the production department, the floor positions are classified and transported, and the accessories and aluminum material positions are divided.
2. Accessories: stainless steel support, corner code, pull rod aluminum, stainless steel indicator lock, stainless steel hinge, door stop aluminum, coat hook.
3. Fastening material: expansion rubber plug, round head or flat head self-tapping screw, glass glue.
4. Main tools: 2 electric drills, 3.5 drill bits, screwdriver bits, power supply, plug-in, vise, glue hammer, measuring ruler, glass glue gun, etc.
5. Operating conditions: (1) The floor materials and wall materials of the bathroom have been installed. (2) Ensure that the corresponding power supply is provided during the construction period.
2. Process flow
On-site wire laying→fixed angle code, foot drilling hole→fixed angle code, foot drilling installation→side plate installation→vertical plate installation→hinge installation→adjustment of door seam fixing pull rod→installation door→installation indicator lock and door Block installation.